-
Welcome
to the webpage for the construction of the Bucklander motorhome...
-
The
first job was to replace the blown cylinder head gasket on the rear bank
of cylinders. This was a major task as the head had to be removed with an
estimated force of about 20 tonnes due to carbon buildup on the cylinder
head bolts where the blow occurred. The head was machined and the fuel injectors
were rebuilt. After reconstruction the motor was found to run very well
(it seemsin very good condition), although there is a vibration to be investigated,
but I am confident this is a dry universal joint in the driveshaft between
the torque converter and gearbox. The vertical exhaust stack was removed,
repaired and reassembled at this point, and repainting was commenced by
myself on the top half of the rear of the unit. Respraying is now being
done by Ron Carratt.
-
Motorhome
construction began in December 2007 with removing the seats and stripping
out the interior. The overhead storage area floor was replaced with timber
as the mesh bottom was damaged and the plastic coating was peeling off the
mesh. The damaged side was removed and the metalwork was straightened and
a new panel was made up. Prior to fitting, the main water tanks were fitted
behind the replaced panel (300 litres). A new diesel generator was then
'shoehorned' into the space beside the motor. A storage area was constructed
over the main fuel tank which is also the access point for water filling,
compressed air outlet and external water tap etc.
-
A
base for the lounge was constructed with storage underneath and a filing
cabinet was put in place beside where the lounge is to be located. Four
of the original bus seats were recovered with leather (the lounge will be
the same) and were refitted in a club seating arrangement. There will be
two tables between the seats. This will also be the main computer centre
for the motorhome, directly behind the drivers seat. As soon as the right
side of the unit is resprayed we will turn it around and the PlugIT office
will then be relocated into the motorhome. This should occur sometime in
March. Weather has not been very conducive to painting!
-
Construction
of the main bedroom then commenced. The original rear 'window' (aluminium)
was made to hinge out at the bottom and a perspex roof was constructed.
A canvas surround was made up to clip in place around the 3 sides. This
can be folded inwards if ever required. This makes up the last 2ft of the
bed. Part of the underbed area was built in as an auxilary water tank (260
litres) and the rest was converted into underbed storage consisting of 4
large drawers, 2 large cupboards and a very large underbed storage area
under the mattress. The central 'island' console was then constructed, which
is one of the main features of the motorhome. Construction of the kitchen
area has commenced with the removal of the first window and wiring being
run up to the rooftop for solar power. Next major project will be fitting
the prefab kitchen which will be ready around the end of February, at which
stage the bulk of the 240 volt wiring can be fitted (some wiring was done
when the generator was fitted).
-
Once
the unit has been repainted on the right side we will be turning it around
and at that point the plumbing and gas installation can commence. There
will be another external door in the left side of the unit.
- April
5th 2008. This marked a milestone in the development of the RV. Except for
a section in the centre of the roof that is to be done in nonslip paint as
a walkway, painting was completed last week Respraying was one of the major
hurdles and this was completed by Ron Carratt with myself as the understudy.
Fitting and setup of all components on the right hand side of the unit were
completed by this morning. These included completion of the generator unit,
the solar battery layout and componentry, the water tank/pressure system/supply
and refilling plus the access door to the main fuel tanks and the storage
unit. It also involved completion of the main bedroom extension as this had
to be completed and folded up to be able to park the RV rearwards in. As a
result we were able to turn the unit around and start on the left side of
the vehicle. This was quite a process as we had to block off the main road
in both directions while the vehicle was reversed out and again when it was
reversed in. Daniel relished the opportunity to use the Stop/Go lollipop sign
(borrowed from my next door neighbour and ex Hornsby Council). We had a fleet
of locals as spectators (it has become quite a celebrity/talking point in
Koolewong and has had quite a few visitors!). Once we had reversed out we
'boarded' the bus for the trip to Woy Woy and a U turn around the roundabout
to be able to reverse in to the driveway. So now work commences on the left
side. Remainder of construction will be divided into 3 main parts plus the
awning (Part 4). Part
1 - underfloor. Underneath the floor the hot water system, toilet receptor
unit, air conditioner compressor unit and the LPG cylinder storage unit will
be fitted. Part 2 - interior. Inside work to
be done involves the completion of the kitchen, fitting of the spa/shower
unit, the toilet/vanity unit and completion of the electrical outlets, both
12 and 240 volts (majority of the electrical work is completed). During this
part of the construction 3 windows will be removed and replaced with fixed
panels and the interior part of the air conditioner will be fitted. I am retaining
the original flurorescent lighting system and supplementing it with 12 volt
downlights throughout. Part 3 - rooftop. This
will involve fitting the solar panels (all wiring is done and the batteries
- inverter are already connected and being used), fitting some storage and
tv/foxtel arial/dish combo (and this is the part that I am in the biggest
quandry over). Part 4 (awning). Design for this
part of construction is pretty well finalised but it is the last item of construction
so will not be started on until most of the rest is completed.
- May
8th 2008. Progress to date: All windows have now been completed and the bathroom
and toilet windows have been installed with 'partial blockout' incorporated
into the window glass. These were a major job as the whole windowframe had
to be 'fabricated' from the existing frames, and the result is something I
am very pleased with. The major project this month has been the completion
of the kitchen and related accessories and I am pleased to report this is
now 98% complete. This was one of the major and most time consuming projects
as the quality of the kitchen can 'make or break' the project, with a lot
of detail work taking a lot of extra time to complete. All drawers and cupboards
are complete (I had the drawer frames made up by a company in West Gosford
and am more than pleased with their expertise and co-operation with what I
was trying to achieve). Also done over this last month has been the solar
collector system. During this time I have been working part time on other
areas: completion of the kitchen involved completing most of the 240 volt
and 12 volt wiring, completion of most of the gas plumbing (the stove and
fridge are the major gas appliances, only other one being the primary hot
water system - the gas cylinder container which will be incorporated under
the floor is 50% done). The solar panels are installed and working plus a
tilt mechanism has been employed to maximise sunlight capture for winter.
A lot of the bathroom preliminary work has beeen done, including installation
of the bathroom flooring, preliminary installation of the vanity unit and
spa bath, drainage for the vanity and spa bath and the washing machine and
electrical wiring for both the bathroom and shower/bath unit. Currently I
am working on the hot water system and I will make some notes on this at the
end of this section. Major work to be completed is as follows: Underfloor
- installation of the gas cylinder reservoir (50% done in the workshop), toilet
reservoir, Air conditioner external unit and auxilary hot water system (completed
by tomorrow). Interior: Completion of
the bathroom and spa/shower unit, the main hot water system and the extra
bench area (including the washing machine and internal air conditioner unit
and additional storage). There is some electrical work to complete, both 240
and 12 volt, but most 240 volt work is done, only waitinng on Jono re earthing.
Roof: Have to replace some damaged roof
panels with some panels that I have had fabricated. this will need at least
4 days of fine weather as I have to open the roof up and will need assistance
from someone (probably Daniel) for this work. Will also be installing the
electric awning at the same time (this is not the external room awning - this
will be one of the last projects and will possibly not be completed until
later in the year).When I remove the roof panels I will also be running power
to the rear area of the unit and this will complete the electrical work. Extras:
I am still 'mulling' over the design of the satellite TV system (mainly how
to simplify the dish setup) but have a fairly good idea what I want to do
and how to achieve it. Apart from this and the external room awning I am still
pretty much on target to finish by the end of June.
- WATER.
When I started this project, one person whose advice I sought was someone
I have known for many years - Phil Leggatt, as he has both vast experience
with trucks and has run a similar sized motorhome for over 12 years. A lot
of his advice has been invaluable, but probably none more so than his advice
on water. His advice was to have as much water capacity as you can, and although
you may not need it often, it can make life a lot easier if you find a spot
you want to stay in - if you have enough water you dont have to pack up and
leave just to replenish your water supply. So, thinking along those lines,
I decided to design the hot water system to be able to uutilise the "best
of both worlds". We have both a spa bath and a shower, and obviously
the spa bath would not be used when you are in a situation where you are trying
to make your water supply spin out to the max. So as the main water heater
I am installing a Trumo gas/240 volt system with a relatively small tank and
a quick recovery cycle. But as an extra I am installing a good old fashioned
Dux domestic non offpeak 50 litre HWS which will feed into the Trumo, so if
you are in a situation where you have plenty of water, you just turn on the
Dux and should have plenty of hot water available. There will be a bit of
trial and error initially, as with the Dux feeding hot water to the Trumo
it will probably be need to be set at a lower water temperature than the Trumo.
If it is not running, the cold water will pass through to the Trumo and it
will be doing all the work.
- July
22nd. After a lot of delays and some problems we are now ready to begin 'road
trials'. We had a few problems, chiefly issues with chinese inverters but
hopefully this issue is behind us. Had to also remove the underfloor watertanks,
all because one tank (of course the hardest to get to :( sprung a leak, and
on getting it out I found a flaw in the moulding in the small tank, which
was actually a new caravan tank. This was fixed and the tanks were refitted.
The bathrooms are now finished except for the mouldings around the windows
- these are a minor detail that will be done later. The satellite dish has
been an overwhelming success. I reverted to a manual setup for the fold and
the elevation tilt which means you set it from up on the roof (see photos
for how we access the roof) but this is no hardship as you tilt the solar
panels at the same time. It is only a small job to set the skew for the LNB
and set the elevation, then come back inside and rotate the dish with the
winder to the required compass heading and watch it locate the best position
on the satfinder guage. After a bit of practice the operation should take
under 10 minutes. Electrical certification was completed succesfully last
month with no issues, initial gas certification was done, but we had to make
some minor alterations, so I am going to Erina hopefully this week for its
final inspection. I have to get a weighbridge certificate for its next registration,
when it will be converted from a motorcoach category to (I assume) an RV category.
After that we can start loading some more gear in. For the recertification
for registration I also have to have an inspection by an RTA certified engineer
(theres only one on the coast!). Things like the seats have to be certified
but I dont anticipate too many issues. This will probably happen next week.
This week I am also intending to take the motorhome down to West Gosford to
be 'fitted' for the sides to the awning (sounds like buying a suit!). The
awnings have also worked out very well - the front awning is a standard domestic
240 volt automated awning (sourced from GraysOnline auctions), but it has
to be folded in in strong winds. The rear awning is the same but I have modified
it with locking arms that allow it to be left out in strong winds and to date
we have had some very strong winds with no problems. With the sides attached
and anchored to the ground it should withstand most wind conditions. Another
major succes has been the air conditioner - it is an NEC inverter unit and
is one of the quietest I have ever seen. We fitted all the front half with
venetians - these seemed to give us the best light control. Spotlight did
the curtains for the rear and for the room divider (and stuffed up the measurements
after coming out and measuring it up, but are going to redo a couple of them),
however they will be good when they are finished.